Lyon’s metro line C, which has been out of service since 2 November because of a fault on the wheels of its trains, will not fully reopen until March 2027 at the earliest. Lyon Mag reports that the operator and the transport authority have announced stronger replacement buses and a new shuttle between Cordeliers and Cuire while new wheels are made.
What happened
According to Lyon Mag, the problem was found on 2 November during preventive maintenance. Staff discovered anomalies on the wheels of every train on line C. Some wheel profiles no longer met the required technical tolerances, which created a safety risk. On 4 November, teams began reprofilage (reprofiling), which means reshaping the wheels to restore their correct form. After a first test on one train, the results were not good enough because new marks appeared on the wheels. RATP Dev, the company that runs the line, then decided to keep the trains out of service.
The timetable was announced at a press conference on Thursday 19 November by Philippe Lopez, managing director of RATP Dev Lyon. He said a full return of the line was not possible before March 2027. “The aim is to get back to safe, lasting and secure operation,” he said, according to Lyon Mag. He also apologised to passengers. Lyon Mag reports that close to 30,000 passengers a day are affected.
Under the new action plan, RATP Dev and SYTRAL Mobilités, the public authority that organises transport in the Lyon area, will replace the faulty wheels with new ones made by a manufacturer in Switzerland. An independent expert review will also study the defects. Its findings will be compared with RATP’s own analysis to identify the cause and set the conditions for a reliable return to service.
Véronique Sarselli, president of the Métropole de Lyon (the metropolitan authority) and of SYTRAL Mobilités, blamed the previous administration. She said a metro renovation plan drawn up in 2023 had not been carried out sufficiently and called the situation “unacceptable”. Bastien Joint, mayor of Caluire-et-Cuire and a SYTRAL Mobilités board member, said residents had been misled about the real state of the network. Gilles Gascon, vice-president of SYTRAL Mobilités, said the new leadership was “taking the hit” and accepting the consequences of earlier choices.
What it means for you
If you normally use line C, you will need other ways to travel for many months. Line C is unusual on the Lyon network: Lyon Mag notes that it climbs slopes of up to 20 percent, and many residents of the Croix-Rousse and Caluire-et-Cuire use it to get to work or study.
Lyon Mag lists these replacement measures:
- Replacement buses have been running every five minutes since the start of this week, and this level of service will continue next week.
- A shuttle over the whole route between Cordeliers and Cuire is due to start by Monday 23 November at the latest. It could start as early as Friday 20 November if conditions allow. It should run every ten minutes, with a journey time of 20 to 25 minutes. Its frequency may be increased if demand requires it.
- Bus line C13 has extra services, especially to serve the Cordeliers and Croix-Rousse areas.
The source does not give the exact route or stops of the replacement buses, so check the operator’s official channels before you travel. Give yourself extra time, especially at peak hours. Lyon Mag also notes that the closure comes in the run-up to the end-of-year holidays, a busy period for shops in the Croix-Rousse and Caluire-et-Cuire. Expect access to these areas from the city centre to be harder than usual.
What to watch next
The first date to watch is the start of the Cordeliers to Cuire shuttle, expected between Friday 20 and Monday 23 November. Next, look out for whether the shuttle’s frequency increases if ten minutes proves too little. The findings of the independent expert review, and how they compare with RATP’s analysis, will decide the conditions for reopening. March 2027 is the earliest possible date for full service, so any update on the delivery of the new wheels from Switzerland will show whether that timetable holds.
Source: Lyon Mag
Sources
- Lyon Mag: Métro C à Lyon : la reprise complète du trafic repoussée à mars 2027 au plus tôt, accessed 19 November 2026