Work on the Seville Metro’s Line 3 is due to reach the Ronda Histórica, the ring road that skirts the city’s old centre, in the first months of 2027, and it is expected to last 36 months. Diario de Sevilla reports that the section will bring traffic diversions for ten Tussam bus lines and temporary land take at several businesses and at the Hospital Cruz Roja.
What happened
Diario de Sevilla describes the plan for “subtramo 4” (section 4) of Line 3, which runs between Pino Montano and Prado. According to the official forecast, construction should begin in the first months of 2027, provided there are no unforeseen problems or last-minute appeals. This stretch is about one kilometre long and includes two new stations: Macarena, at Muñoz y León, and Capuchinos, at the junction with avenida de la Cruz Roja. The Andalusian regional government’s transport department, the consejería de Fomento, says the northern half of Line 3 will be operating in 2030.
The paper notes that residents and shopkeepers along this stretch have so far been relatively calm. That contrasts with the protests in the previous section, on avenida Doctor Fedriani and San Juan de Ribera.
The construction project (proyecto constructivo) sets out several effects:
- Temporary use of land at the La Pastora fried-fish and leisure business, at the Capuchinos petrol station and at the emergency area of the Hospital Cruz Roja. Compensation for the works as a whole totals 168,210.09 euros.
- Traffic diversions for ten Tussam lines (the city bus company) and for private vehicles.
- Intensive archaeological digs along the final two sections, from calle La María to the Jardines del Valle, estimated at six months.
Hospital, shops and petrol station
At the Hospital Cruz Roja, the works need 65 square metres, affecting the access gate, a low wall, fencing, a tall hedge and a lawn. The project itself says access to the emergency department on Ronda de Capuchinos is “affected in an important way” by the Capuchinos station. Its proposed answer is temporary ambulance access via avenida Cruz Roja.
La Pastora, a business held on a municipal concession (concesión del Ayuntamiento) since 1924, loses 58 metres. Its operators, the Maldonado family, told the newspaper they do not plan to close and that nobody from the Junta de Andalucía or the Ayuntamiento had told them they were affected. They say they will keep opening from Semana Santa (Holy Week) until after summer if enough pavement remains for customers to reach the terrace.
The Capuchinos petrol station stays open, but according to the project the car wash tunnel will be inaccessible for at least five months. Six kiosks will be relocated: three newspaper kiosks, two ONCE kiosks and one sweet kiosk, on Ronda de Capuchinos (numbers 2, 3, 13 and 19) and at María Auxiliadora 19.
What it means for you
If you drive, cycle or take the bus around the north of the old town, expect changes for roughly three years from 2027. The project defines three phases:
- Phase 1 (diversion of utilities and station building) and Phase 3 (interior excavation): one lane in each direction stays open. Only public transport, residents, garages and emergency vehicles may use the avenue, and private traffic goes by the back streets.
- Phase 2 (tunnel slab and walls): only one lane stays open, towards the centre. Buses are diverted through back streets to run in the opposite direction, centre to Barqueta.
The Tussam lines affected by the Barqueta-bound closure are 1, 10, 11, 12, 15, 16, C1, C2, C3 and C4. In Phase 2 their alternative route runs along La Florida, Amador de los Ríos, Arroyo, Almadén de la Plata, the Miraflores junction, Previsión, Fray Isidoro de Sevilla and San Juan de Ribera.
Private traffic that is not for residents or garages is diverted in the Barqueta to centre direction in all phases. The route uses San Juan de Ribera, Dr. Leal Castaños, Sor Francisca Dorotea, Ronda de Pío XII, avenida de Llanes, Alcalde Manuel del Valle, Tharsis, Arroyo, Gonzalo Bilbao and Recaredo.
Practical steps for residents:
- If you live or work near Capuchinos, Macarena or María Auxiliadora, check which Tussam lines you rely on and note whether they are on the list above.
- If you use the emergency department at Hospital Cruz Roja, be aware that ambulance access is planned via avenida Cruz Roja during the works.
- If you run a business or rent premises on the affected stretch, ask the Ayuntamiento or Junta de Andalucía directly about land take and compensation, as the La Pastora operators say they have heard nothing.
What to watch next
The start date of 2027 depends on there being no unforeseen events or last-minute appeals, according to the newspaper. The six-month archaeological phase could also change if problems arise. The areas of high archaeological risk lie between calle La María and calle Doctor Relimpio, opposite the Jardines del Valle, where Diario de Sevilla says remains could include a late Roman necropolis and traces of the city wall. Watch for official announcements of exact dates, bus rerouting and signed access to the hospital and petrol station.
Source: Diario de Sevilla
Sources
- Diario de Sevilla: El impacto de la obra del Metro de Sevilla en la Ronda Histórica, accessed 14 November 2026