The A99, the motorway ring around Munich, is fully closed on its eastern section between the München-Süd and München-Ost interchanges while a damaged bridge near Haar is demolished. According to tz, the first day of the closure went smoothly, with far less traffic than usual.
What happened
tz, citing the news agency dpa, reports that major construction work began at the weekend on the eastern part of the Münchner Autobahnring (Munich’s motorway ring). The A99 is fully closed between the Autobahnkreuz (motorway interchange) München-Süd and the Autobahnkreuz München-Ost. The closure is needed to demolish a bridge that crosses the motorway near Haar, a municipality on the eastern edge of Munich. The information comes from the Autobahn GmbH für Südbayern, the southern Bavaria branch of the federal company that runs Germany’s motorways.
The bridge had to come down because it showed serious damage from age. The report explains that it must be removed completely in one continuous operation so that debris cannot fall onto the carriageway in an uncontrolled way. Between 50 and 60 specialist workers are working around the clock with several excavators.
Michael Kordon, director of the Südbayern branch of the Autobahn GmbH, said the organisers deliberately chose a date outside school holidays and with no major events in the city. According to Sabine Wiedemann, head of bridge modernisation at the motorway company, only a third of the usual traffic was measured on the first day. Kordon said large-scale warning signs made a major contribution to this. They were switched on as far away as Nürnberg (Nuremberg) and by Asfinag, the Austrian motorway operator.
What it means for you
If you drive in or around Munich, expect the eastern A99 between München-Süd and München-Ost to be unavailable until the demolition is finished. tz reports that the motorway should reopen early on Monday morning, provided everything goes to plan. Wiedemann said she was confident the schedule would be kept, and Kordon said the crews want to finish quickly.
The closure does not only affect motorway users. According to the report, the remaining through traffic has to travel through the city itself and through the Landkreise (districts) of München, Ebersberg and Erding. That means the wider Munich area is still affected, even with fewer drivers on the road. If you live in or commute through Haar, the eastern city districts, or towns in these three districts, you may see heavier traffic on local roads than usual.
Practical steps based on the source:
- Avoid the A99 between München-Süd and München-Ost until the closure ends, and plan a different route if you normally use it.
- Allow extra time for journeys through eastern Munich and the districts of München, Ebersberg and Erding, where diverted traffic is expected.
- Look out for the motorway information signs, which are already showing details of the closure on approach roads.
- Check that the motorway has actually reopened before you set off on Monday morning, as the reopening depends on the work going to plan.
tz does not give details of official diversion routes, public transport alternatives or any costs for drivers.
What to watch next
The main thing to watch is whether the A99 reopens early on Monday morning as planned. tz reports that work on a replacement bridge, called an Ersatzneubau (replacement new build), will start straight after the demolition. The new bridge is due to be completed by 2028.
Until then, traffic crossing the motorway at this point will use a temporary Behelfsbrücke (temporary bridge). The report does not say whether the construction of the new bridge will need further closures of the A99, so residents who use this section regularly should look out for future announcements from the Autobahn GmbH.
Source: tz
Sources
- tz: Bauarbeiten auf A99 bei München haben begonnen – Autobahn gesperrt, accessed 21 November 2026
Munich, for internationals
One email a week: what changed for internationals in Munich, the week's news from Germany, and one guide worth reading. No spam, unsubscribe any time.








Comments 1